Oasis Tower 2: срок сдачи и ход строительства
Oasis Tower 2 by Pal
Коротко
Oasis Tower 2 is a residential project by Pal in Al Hebiah Fourth, registered with Dubai Land Department as project 1560 with 444 units. The latest DLD inspection (5 Sep 2026) recorded 74% construction progress, and the registered completion date is June 2027.
Обновлено RERA ORN 1653674
Source: Dubai Land Department project register. This page currently covers 811 residential and mixed-use projects that were registered, started, due or completed in 2026; earlier launches are added as the full register is loaded.
Подробные цифры и таблицы на этой странице опубликованы на английском языке.
Construction & handover
From the Dubai Land Department project register.
- Status
- Under construction
- Planned completion (DLD)
- June 2027
- Construction progress
- 74% inspected 5 Sep 2026
- Developer
- Pal
- Homes
- 444 units
- Registered project value
- AED 92.5M
- Escrow account
- Registered
- DLD project number
- 1560
PROJECT CONSISTS OF 3B+G+25 RESIDENTIAL BUILDING LOCATED IN AL HEBIAH FOURTH. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.
Legal developer: P A L DEVELOPMENTS L.L.C · Escrow account no. 10213831159001
What off-plan homes sell for in Al Hebiah Fourth
Registered off-plan sales across Al Hebiah Fourth this year, a guide to what a launch here is likely to be priced at.
Other new projects in Al Hebiah Fourth
| Project | Developer | Homes | Handover | Built |
|---|---|---|---|---|
| Elysian Mansions | Majid Al Futtaim | 35 | Mar 2025 | Not reported |
| Mag 777 50 sales | Dng | 266 | Jan 2026 | 67% |
| Sportz By Danube 53 sales | Danube | 1,110 | Mar 2026 | Not reported |
| Binghatti Haven 88 sales | Binghatti | 501 | Mar 2026 | 76% |
| Urban Park Residences 27 sales | Urban Venture | 187 | Apr 2026 | 68% |
| Lime Light Twin Towers | Lime Light | 734 | Jun 2026 | Not reported |
| Alaya | Majid Al Futtaim | 46 | Jul 2026 | Not reported |
| LANAI Island | Majid Al Futtaim | 13 | Sep 2026 | Not reported |
| Sartoria | Pinnacle A K S | 224 | Oct 2027 | 51% |
Common questions
When is the handover of Oasis Tower 2?
The completion date registered with Dubai Land Department is June 2027. The latest DLD inspection (5 Sep 2026) recorded 74% construction progress. Developers can revise this date with DLD approval.
Who is the developer of Oasis Tower 2?
Oasis Tower 2 is developed by Pal (registered as P A L DEVELOPMENTS L.L.C).
Is Oasis Tower 2 registered with DLD?
Yes. It is DLD project number 1560, with escrow account 10213831159001. Current status: active.
How much do off-plan homes cost in Al Hebiah Fourth?
Off-plan homes in Al Hebiah Fourth sold for a median of AED 2,130 per sq ft in 2026, across 26 registered sales.
Где находится Oasis Tower 2, Al Hebiah Fourth?
Местоположение показано на уровне района; точный адрес здания уточните у консультанта.
Уведомления о ценах: Al Hebiah Fourth
Короткий ежемесячный отчёт в WhatsApp: новые цены сделок, продажи и запуски.
Поговорить с консультантом
Получите чёткий ответ
Расскажите, что вы ищете. Ответим в течение рабочего часа: варианты, свежие цены сделок и вопросы, которые стоит задать.
- ✓ Цены сверены с регистрациями DLD
- ✓ Консультанты с лицензией RERA (ORN 1653674)
- ✓ Без обязательств и спама