Palm Central Private Residences - Frond D: موعد التسليم ونسبة الإنجاز
Palm Central Private Residences - Frond D by Nakheel
الإجابة المختصرة
Palm Central Private Residences - Frond D is a residential project by Nakheel in Palm Jabal Ali, registered with Dubai Land Department as project 4613 with 216 units. The latest DLD inspection (2 Nov 2026) recorded 0% construction progress, and the registered completion date is October 2030.
آخر تحديث رقم ريرا للمكتب 1653674
Source: Dubai Land Department project register. This page currently covers 811 residential and mixed-use projects that were registered, started, due or completed in 2026; earlier launches are added as the full register is loaded.
الأرقام والجداول التفصيلية في هذه الصفحة منشورة باللغة الإنجليزية.
Construction & handover
From the Dubai Land Department project register.
- Status
- Under construction
- Planned completion (DLD)
- October 2030
- Construction progress
- 0% inspected 2 Nov 2026
- Developer
- Nakheel
- Homes
- 216 units
- Registered project value
- AED 506.9M
- Escrow account
- Registered
- DLD project number
- 4613
Residential Buildings comprising of 216 Residential units (1BHK=86, 2BHK=70, 3BHK=40, 4BHK=8, 4BR TH = 8, 5BR= 2, 5BR PH=2) - Building A : B+G+7+R (78 Residential Units). - Building B: B+G+7+R (78 Residential Units). - Building C: B+G+7+R (60 Residential Units).
Legal developer: THE PALM - JEBEL ALI CO. (L.L.C) · Escrow account no. 29691325
What off-plan homes sell for in Palm Jabal Ali
Registered off-plan sales across Palm Jabal Ali this year, a guide to what a launch here is likely to be priced at.
More by Nakheel
| Project | Area | Homes | Handover | Built |
|---|---|---|---|---|
| Jebel Ali Village | Jabal Ali First | 278 | Apr 2026 | 100% |
| Jebel Ali Village Townhouses- Phase 1 | Jabal Ali First | 286 | Apr 2026 | 100% |
| Jebel Ali Village Townhouses - Phase 2 | Jabal Ali First | 132 | Apr 2026 | 100% |
| Jebel Ali Village Townhouses - Phase 3 | Jabal Ali First | 196 | Apr 2026 | 100% |
| Bay Residences Dubai Islands | Dubai Islands | 302 | Oct 2026 | 48% |
| Palm Central Private Residences - Frond M 127 sales | Palm Jabal Ali | 212 | Jul 2029 | 0% |
| Bay Estate | Dubai Islands | 357 | Aug 2030 | 0% |
| Palm Central Private Residences - Frond N 211 sales | Palm Jabal Ali | 222 | Dec 2030 | 0% |
Other new projects in Palm Jabal Ali
| Project | Developer | Homes | Handover | Built |
|---|---|---|---|---|
| Palm Central Private Residences - Frond M 127 sales | Nakheel | 212 | Jul 2029 | 0% |
| Palm Central Private Residences - Frond N 211 sales | Nakheel | 222 | Dec 2030 | 0% |
Common questions
When is the handover of Palm Central Private Residences - Frond D?
The completion date registered with Dubai Land Department is October 2030. The latest DLD inspection (2 Nov 2026) recorded 0% construction progress. Developers can revise this date with DLD approval.
Who is the developer of Palm Central Private Residences - Frond D?
Palm Central Private Residences - Frond D is developed by Nakheel (registered as THE PALM - JEBEL ALI CO. (L.L.C)).
Is Palm Central Private Residences - Frond D registered with DLD?
Yes. It is DLD project number 4613, with escrow account 29691325. Current status: active.
How much do off-plan homes cost in Palm Jabal Ali?
Off-plan homes in Palm Jabal Ali sold for a median of AED 3,512 per sq ft in 2026, across 338 registered sales.
أين يقع Palm Central Private Residences - Frond D, Palm Jabal Ali؟
احصل على تنبيهات الأسعار في Palm Jabal Ali
تحديث شهري قصير عبر واتساب: أحدث الأسعار المسجّلة والصفقات والإطلاقات.
تحدّث إلى مستشار
احصل على إجابة واضحة
أخبرنا بما تبحث عنه. نرد خلال ساعة عمل واحدة بخيارات وأسعار مسجّلة حديثاً والأسئلة التي تستحق الطرح.
- ✓ أسعار مُتحقَّق منها مقابل تسجيلات الدائرة
- ✓ مستشارون مسجّلون لدى ريرا (رقم المكتب 1653674)
- ✓ دون التزام ودون رسائل مزعجة