Holm Central: موعد التسليم ونسبة الإنجاز
Holm Central by Holm Avenue
الإجابة المختصرة
Holm Central is a residential project by Holm Avenue in Al Satwa, registered with Dubai Land Department as project 4554 with 461 units. The latest DLD inspection (24 Aug 2026) recorded 0% construction progress, and the registered completion date is June 2028.
آخر تحديث رقم ريرا للمكتب 1653674
Source: Dubai Land Department project register. This page currently covers 811 residential and mixed-use projects that were registered, started, due or completed in 2026; earlier launches are added as the full register is loaded.
الأرقام والجداول التفصيلية في هذه الصفحة منشورة باللغة الإنجليزية.
Construction & handover
From the Dubai Land Department project register.
- Status
- Under construction
- Planned completion (DLD)
- June 2028
- Construction progress
- 0% inspected 24 Aug 2026
- Developer
- Holm Avenue
- Homes
- 461 units
- Registered project value
- AED 165M
- Escrow account
- Registered
- DLD project number
- 4554
G+2P+8+R
Legal developer: HOLM AVENUE REAL ESTATE DEVELOPMENT L.L.C · Escrow account no. 0205933054509
What off-plan homes sell for in Al Satwa
Registered off-plan sales across Al Satwa this year, a guide to what a launch here is likely to be priced at.
More by Holm Avenue
| Project | Area | Homes | Handover | Built |
|---|---|---|---|---|
| Linea by Holm 194 sales | Al Satwa | 210 | Jun 2028 | 18% |
Other new projects in Al Satwa
| Project | Developer | Homes | Handover | Built |
|---|---|---|---|---|
| The Grandala 10 sales | Palladium Prime | 86 | Jan 2026 | 91% |
| 161 Jumeirah Lane | National | 161 | Mar 2026 | 70% |
| ONAYA RESIDENCES By Kaya | Kaya | 41 | Jun 2026 | 38% |
| Enso Jade 105 sales | Enso | 105 | Jun 2026 | 42% |
| Enso Amber 29 sales | Enso | 71 | Jun 2026 | 11% |
| Evergrin House 14 sales | Object 1 | 219 | Jun 2026 | 55% |
| Cavara Central 18 sales | Cavara | 166 | Jul 2026 | 43% |
| Brand Centro | Ems | 56 | Jul 2026 | 90% |
| Jardin Astral | Galaxy Realty | 46 | Aug 2026 | 45% |
| Mayfair Gardens by Majid 10 sales | Majid | 64 | Aug 2026 | 70% |
Common questions
When is the handover of Holm Central?
The completion date registered with Dubai Land Department is June 2028. The latest DLD inspection (24 Aug 2026) recorded 0% construction progress. Developers can revise this date with DLD approval.
Who is the developer of Holm Central?
Holm Central is developed by Holm Avenue (registered as HOLM AVENUE REAL ESTATE DEVELOPMENT L.L.C).
Is Holm Central registered with DLD?
Yes. It is DLD project number 4554, with escrow account 0205933054509. Current status: active.
How much do off-plan homes cost in Al Satwa?
Off-plan homes in Al Satwa sold for a median of AED 2,296 per sq ft in 2026, across 1,159 registered sales.
أين يقع Holm Central, Al Satwa؟
احصل على تنبيهات الأسعار في Al Satwa
تحديث شهري قصير عبر واتساب: أحدث الأسعار المسجّلة والصفقات والإطلاقات.
تحدّث إلى مستشار
احصل على إجابة واضحة
أخبرنا بما تبحث عنه. نرد خلال ساعة عمل واحدة بخيارات وأسعار مسجّلة حديثاً والأسئلة التي تستحق الطرح.
- ✓ أسعار مُتحقَّق منها مقابل تسجيلات الدائرة
- ✓ مستشارون مسجّلون لدى ريرا (رقم المكتب 1653674)
- ✓ دون التزام ودون رسائل مزعجة